HomeMy WebLinkAbout05 Business Services Report 6, 11 Oct 2000OTTAWA- CARLETON DISTRICT SCHOOL BOARD
TO: Board of Education DATE: 11 October 2000
A meeting of the Business Services Committee was held this evening at 133 Greenbank
Road, Nepean, commencing at 7.45 pm, in the Trustees' Committee Room, with Trustee Morse in
the chair and the following in attendance:
MEMBERS: Trustees Lynn Graham, Jim Libbey, and Norm MacDonald (by
phone)
ALSO PRESENT: Trustees Albert Chambers (by phone), Alex Getty, Patty Anne Hill,
Sheryl MacDonald, and Lynn Scott
STAFF: Jim Grieve, Director of Education and Secretary of the Board
Rose -Marie Batley, Superintendent of Facilities & Physical
Planning
Michael Clarke, Superintendent of Finance
Judy Turriff, Superintendent of Schools
Michael Carson, Manager, Physical Planning & Transportation
Kathy Lausman, Manager of Physical Facilities & Design and
Construction Services
Brenda Cooper, Committee Coordinator
REPRESENTATIVES: Bill Hollingsworth, Ottawa Carleton Secondary School
Administrators' Network
Janice Ritchie, Ottawa - Carleton Assembly of School
Councils
Dave Seymour of DukeSolutions was also present for most of the meeting. He left about
10:30 pm as it was evident that the debate on the Long Term Accommodation Plan would continue
for some time.
On a motion by Trustee Getty, the agenda was approved as presented.
Pierre Boivin, Co-Chair of the Elgin Street Public School Council, described his
real estate experience. He suggested that a win - win -win scenario would be the
result for the urban, suburban, and rural areas of the OCDSB if the Board were
to approve a motion that the final decisions on school closures be made only
after conducting "proper" program review and long term capital planning
exercises with thorough and open consultations with the affected
constituencies.
Business Services Committee - 1 - 11 October 2000
The Chair indicated that it would be seen during the upcoming meetings on
school closures whether a trustee wished to place such motion on the floor.
(b) Administrative Facilities
Joan Spice of the Elgin Street Public School Council remarked that she believes
that an unrealistic provincial formula for pupil accommodation is causing the
Board to consider closing schools. She suggested that other ways be found to
generate funds through a long term plan for the management of administrative
property. For example, she questioned the value of storing old furniture. In
addition, she noted that the Gilmour Street building is a valuable downtown
property and asked why it is not for sale yet.
Superintendent Batley reported that staff are undertaking a study of
administrative property, and that the space needs of the Plant Department are
still to be finalized. With respect to the Gilmour Street property, it is in the
disposal process now. It is the Board's policy to dispose of furniture as quickly
as possible, and schools have been able to use much of the surplus.
Ginny Fobert of West Carleton pointed out that there will be no money freed up
unless school closure decisions are made and schools closed. She indicated that
she does not understand why the Board appears to be hesitant to make this
important decision.
Noting that there are a number of problems outside the greenbelt, Ms Fobert
asked what plans the Board has to "level the playing field" for students in
suburban and rural areas.
The Director observed that there is no simple answer, and that pupil
accommodation is only one component to be considered. He noted that the
budget committee, which started meeting last month, is providing input to staff
for the development of a budget which will provide for and acknowledge
differences in the distribution of resources. He noted that the Ottawa - Carleton
Assembly of School Councils is playing a role through its representation on the
budget committee.
Note: During the following item, Trustee Libbey assumed the Chair whenever Trustee Morse
wished to participate in the debate.
Your Committee had before it for consideration staff report 00 -210 presenting for
submission to the Ministry of Education, the OCDSB's interim Long Term Accommodation Plan
(LTAP).
Michael Carson introduced the report, highlighting the process required to complete
the LTAP, and plans to bring forward a work plan in February 2001. He noted that the report
focuses on elementary facilities, because the impact of secondary school reform must be
addressed before a plan is developed.
Business Services Committee - 2 - 11 October 2000
School boards across the province are at various stages in their development of plans,
(W with some having complete plans, and others not having begun. Staff feel comfortable with
submitting an interim report with plans for the future process to the Ministry of Education.
Mr. Carson noted that there is a significant backlog of work to be done on existing
schools and that when a recognized list is brought forth, it will recognize and identify the full
range of capital and maintenance needs.
In response to a request by Trustee Morse, staff agreed to provide trustees with current
data along with the projections outlined in the table on folio 3.
Trustee Libbey moved the recommendation in the staff report, adding part C, viz:
A. THAT the Board direct staff to submit the OCDSB's interim Long Term
Accommodation Plan (LTAP) to the Ministry of Education;
B . THAT staff proceed with the preparation of the Facilities Master Plan in
accordance with the process outlined in the LTAP; and
C. THAT staff produce a detailed accommodation work plan for consideration by
the Board in February 2001, and that the plan set out clearly, among other
things, the timelines for constructing new schools and additions to be opened
commencing in September 2002, with a two -month contingency provision.
In response to queries, Mr. Carson reported that the first part of part C would not be a
problem. The second part would present difficulties, depending on how long it takes to gather
(W information and to get input when establishing the priorities. It would also require shortening
a number of items in the work plan.
On a motion by Trustee Scott, Part C was amended by changing September 2002 to 2001.
It was noted that this was a starting point which would not affect the Longfields- Davidson
Heights project. Trustee Libbey withdrew the last clause regarding a two -month contingency
provision with the agreement of the Committee.
A friendly amendment by Trustee Graham was added later, viz:
D. THAT the workplan set out the timelines for renewals and renovations
commencing in September 2001.
A lengthy debate ensued, during which a several clarifications were provided, and a
number of amendments proposed.
Staff clarified that the Long Term Accommodation Plan is the Board's plan and that a
copy is being sent to the Ministry of Education, but it is not a report to the Ministry. Staff do not
expect that additional interim reports will be issued.
With respect to the school facility survey described on folio 80, Janice Ritchie advised
that some school councils have refused to participate because there do not appear to be any
standards, and because they do not know how the survey will be used. Superintendent Batley
reported that this is a Ministry- mandated survey, not a Board one. The survey is required
annually, and the results will be posted on the Ministry's website.
Business Services Committee - 3 - 11 October 2000
The areas of concern emphasized during debate were anomalies in the retention rates,
the need for more detail on the renovation and renewal projects required for existing schools
across the system, and the assumption that school closures will take place. Staff recalled that
trustees had been advised during other meetings that the LTAP would be based on school closure
assumptions.
The first two concerns were addressed in amendments (a) and (d) below. With respect to
the third concern regarding school closure assumptions, Trustee Chambers moved THAT
appendices A and B be removed. Appendix A is a summary of elementary accommodation needs
by family of schools, and Appendix B gives current and projected elementary needs in
accordance with school closure recommendations. The amendment was defeated.
There was also concern that there was no indication of a plan for an addition to
Stonecrest Elementary School. Staff advised that detail will be developed in the work plan.
The following is a list of the approved amendments to the interim Long Term
Accommodation Plan:
(a) (Amendment by Trustee Norm MacDonald, sub - amendment by Trustee Morse)
Add to folio 3 under Pupil Place Shortages, a comment indicating that historic
retention rates in many areas have changed due to several factors, and this may
be reflected in the numbers. For example, it was felt that reduced transporta-
tion provisions and a lack of facilities at the OCDSB attracts students to the
coterminous boards.
(b) (Friendly amendment by Trustee Chambers)
Remove appendix D from the submission to the Ministry and from the reference
in the last sentence in the first paragraph of the text to a copy being attached
(appendix D is a Ministry document provided for the information of trustees).
(c) (Friendly amendment by Trustee Chambers)
With respect to the proceeds of sales, a reference to non - school buildings and
sites is to be added.
(d) (Friendly amendment by Trustee Graham)
Information regarding the existing accommodation needs of the system, i.e.,
renovations and renewals, is to be strengthened and expanded.
(e) (Friendly amendment by Trustee Sheryl MacDonald)
Information is to be added on folios 11 and 12 highlighting Crystal Bay's and
Clifford Bowie's role as schools for the developmentally disabled.
( f ) (Amendment by Trustee Libbey)
Add a bullet (no descriptors) at the end of the Sources of Funding section, viz:
Innovative Approaches Where Feasible.
Business Services Committee - 4 - 11 October 2000
/L
(g) (Friendly amendment by Trustee Libbey)
Change the second bullet on folio 7 to: The plan, containing recommendations
for prioritized expenditures and public consultation will be presented to trustees
and the public. Note: the rest of the sentence is to be eliminated.
(h) (Friendly amendment by Trustee Graham)
A new first bullet is to be inserted in the criteria, folio 7, viz: program
requirements.
(i) (Friendly amendment by Trustee Graham)
A new bullet is to be added to the end of the list of criteria on folio 7, viz:
partnership opportunities.
At the request of Trustee Getty, a separate vote was held on each part of the motion.
Part A, as amended, and Part B were carried. Parts C and D were defeated.
On a motion by Trustee Libbey, therefore, your Committee recommends:
A. THAT THE BOARD DIRECT STAFF TO SUBMIT THE OCDSB'S INTERIM
LONG TERM ACCOMMODATION PLAN (LTAP), AS AMENDED, TO THE
MINISTRY OF EDUCATION (APPENDIX A) *; AND
B . THAT STAFF PROCEED WITH THE PREPARATION OF THE FACILITIES
MASTER PLAN IN ACCORDANCE WITH THE PROCESS OUTLINED IN
THE LTAP.
*Note: The amended text, not the entire LTAP document, is attached; the appendices are
included with staff report 00 -210 to the Business Services Committee (reference the
committee's agenda of 11 October 2000). The text and the appendices will be sent to the
Ministry of Education as the OCDSB's interim Long Term Accommodation Plan.
4. Better Schools fit• t • Facilities- and Physical Planning __t
By consensus, the item on the better schools partnership was deferred to the next
meeting.
On a motion by Trustee Scott, it was agreed to continue the meeting past 11:00 pm to
receive an update on the Provincial Transportation Funding Committee.
Michael Carson reported that John Grochot has made it clear to the Ministry at
meetings of the Provincial Transportation Funding Committee, and staff has made it clear in
correspondence, that the OCDSB needs the new transportation funding model now in order to
prepare its budget for the 2001 -02 school year.
Business Services Committee - 5 - 11 October 2000
There has been no response to the letter, but staff has been advised verbally that the
grant regulations are always released in March, and that this is when the transportation
funding formula will be available. Staff indicated to the Ministry that this is unsatisfactory,
and will follow up with a letter from the Director this week.
In response to a query, Mr. Carson reported that the letter from the Director will
identify concern that a change in the formula could have a substantial effect on the amount of
money available to the Board, either negatively or positively, right at the end of the Board's
budget deliberations. It will also be noted that changes may significantly affect the Board's
policies on student transportation.
Trustees shared staff's concern that the proposed delivery of the new transportation
funding formula in March 2001 will be much too late for budget or policy decisions. They felt
that it was now time to address this situation at the political level. Accordingly, Trustee Scott
gave notice that she will present a motion at the 23 October Board meeting recommending that
the Board write to the Minister of Education outlining the consequences to school boards of
receiving the transportation funding formula so late.
7. Results of Mirror Netting for the Year 1999 -2000
Your Committee noted for information staff report No. 00-213 providing the results of
mirror netting for the year 1999 -2000. Under this voluntary program, the Board "borrows" funds
from school and education development charges bank accounts, and pays these accounts the
same interest as the Board pays to the bank. Schools earned $147,204 from the mirror netting
program last year. The education development charges account earned $355,782.
The meeting adjourned at 11:30 pm.
Pam Morse, Chair
Business Services Committee
BLC /cb
BSC /001011
Business Services Committee - 6 - 11 October 2000
r,iDF&I'JL ih; tq
/a`-
REPORT ON LONG TERM ACCOMMODATION PLANNING
INTRODUCTION
As part of the Ministry of Education's Accountability Framework for Pupil Accommodation Grants,
boards are expected to develop a long -term plan to address the accommodation needs of their students. A
The Ottawa- Carleton District School Board is faced with the challenge of providing appropriate facilities for
its students within the constraints of the new Ministry funding model. To meet this challenge, the Board
needs to develop a Plan that will provide mechanisms and strategies for the construction of new schools,
major capital renovations and the use of temporary accommodations such as portables and portapaks.
Development of the Long Term Accommodation Plan is ongoing. The Ministry has indicated that it
expects plans to be updated at least every five years; however, it is likely the plan will need more
frequent revisions, depending on school closure decisions at the elementary level, as well as the outcome
of the secondary accommodation review.
The Plan will ultimately address the following six issues:
A) updated 15 year enrolment projections by school, and by family;
B) the need for new schools;
C) the costs associated with new schools and the funding arrangements in place;
D) consolidation of surplus pupil spaces;
E) the need to address the condition of existing schools; and
F) the processes to be used in setting priorities.
The Board has already begun to address a number of these issues.
Since 1998, the Board has been addressing the need to consolidate pupil spaces and has been involved in
school closure processes at the elementary level. Should Board approve the recommendations contained
in Report No. 00 -187, it will have reduced the number of spaces at the elementary level by 5,008 across
the Board since 1998. Coupled with Ministry adjustments to capacity figures based on changes in loading
of relocatable modules and reduced class sizes which resulted in a reduction of an additional 5,599
spaces, the Board would be eligible to receive Grants for New Pupil Places in the 2001 -02 school year.
Further, the Ministry has amended the Regulations with respect to funds collected under previous EDC
bylaws to allow those funds to be used to construct new schools, while a Board does not have a new
bylaw in place. This amendment has allowed the Board to proceed with planning to build its first
elementary school in Longfields /Davidson Heights.
Upon completion of the current Area Review / School Closure process, staff will continue with
development of the Facilities Master Plan.
It should be noted that for illustrative purposes, this report focuses on needs at the elementary panel. The
Board faces the same pressures at the secondary level, and staff will be bringing forward a plan and
timelines for the review of secondary accommodation levels in January 2001.
(As amended at Business Services Committee, October 11, 2000 - changes in italics)
13-
DETERMINATION OF NEEDS
MEETING ENROLMENT GROWTH
To illustrate the needs the Board will be facing, staff has developed preliminary enrolment projections for
the elementary panel. These projections have been prepared for the proposed families of schools, both
inside and outside the Greenbelt and are summarized in Appendices A and B. These projections are
based on the projections of school -age population prepared by staff of the Regional Municipality of
Ottawa- Carleton. These projections will need to be reviewed and updated on a school by school basis
during the development of the facilities master plan and in conjunction with the development of an
Education Development Charges by -law. The projections are estimates and will not necessarily tie in to
the data supplied in the Report # 00 -187 Recommendations for Elementary School Closures (Inside the
Greenbelt).
In some cases, projections reflect a participation rate which is lower than would have been expected in the past. This
reduction may be due to accommodation shortages and other policy issues such as transportation. As a result, the
projection may underestimate the ultimate need for pupil places.
Pupil Place shortages
The data in Appendix I indicate that there will be a shortage of approximately 3,322 elementary pupil
places in six of the families of schools in 2004:
A Gloucester SUC and Leitrim
B Goulbourn
C Kanata
D Nepean SUC
E Osgoode
F West Carleton
TOTAL
2000
2004
2009
2014
83
483
983
1483
196
291
407
352
608
844
895
1053
710
1192
1788
2387
140
213
173
339
193
362
237
336
1950
3322
4628
5848
This need increases to 4,628 spaces in 2009, and to 5,848 by 2014. (These figures do not reflect the capacity
added by the recently approved school in Longfields /Davidson Heights.) Based on Ministry benchmark,
the construction cost of providing all of these spaces would be in excess of $68 M. As these costs exceed
the funds that will be generated through Grants for New Pupil Places, it is likely that some of these
students will continue to be served in temporary settings.
A) This area, primarily the new Riverside South community, is experiencing rapid growth. Students
are currently directed to Manotick P.S. which has added to the overcrowding in that school.
Recent decisions by Regional Council to accelerate servicing to the Leitrim area may mean that
the growth in this area may occur more rapidly than originally expected.
B) Trustees are aware of the overcrowding issues in Stittsville, which have resulted in the
redirection of JK students from A. Lorne Cassidy to Munster. Projections of school -age
population show an increase to 2009, but declining by 2014. This is due to a limit on the number
of units allowed due to servicing restrictions currently in effect in Stittsville. Should the current
development pressures result in changes to the Regional Official Plan, there would be a
continued increase in the school -age population.
(As amended at Business Services Committee, October 11, 2000 - changes in italics)
/I-
C) Since 1991, Kanata has seen substantial residential development, accounting for nearly 25% of
units built in the suburban areas in that time. Residential development continues to be strong and
(W the existing shortage of pupil places is expected to continue to increase as a result of the new
development, although it will be slightly offset by the maturing of neighborhoods south of the
Queensway.
D) South Nepean and mainly Longfields /Davidson Heights have experienced almost an equal
amount of increased residential development as that of Kanata in the period since 1991. This is
expected to continue; the current Regional Official Plan anticipates that approximately 25% of
suburban housing starts will occur here in the period of 1996 -2021. The Board has already
authorized the construction of a new school in the area. This school will ultimately provide
approximately 700 spaces to begin to address the shortages noted above.
E) The Osgoode family of elementary schools will continue to experience steady growth during the
15 -year period. Plans to accommodate this growth will need to consider some of the existing site
constraints as well as the transportation times and distances involved.
F) West Carleton currently has an overall shortfall of approximately 213 spaces and the need for
intermediate spaces at Stonecrest has been previously documented. The regional projections
show continued growth in the school -age population in this family; however, it should be noted
that the housing starts assumed in the official plan have not been achieved to date, which could
result in a slower growth rate. On the other hand, there is some discussion that the current
growth in Kanata's high -tech sector may result in increased construction activity in West
Carleton.
Prior to recommending priorities, a detailed review of these areas will be required considering options
which may include:
• Additions to existing schools
• Continued use of portables or portapaks
• Boundary adjustments and transporting students to make use of existing surplus
spaces
• Acquisition of sites and construction of new schools
The options will need to be evaluated in light of a number of criteria which tend to be inter- related and
would include:
1) the current and anticipated enrolment levels;
2) constraints on existing sites with regard to accommodating additional portables;
3) suitability to accept additions; and
4) enrolment trends in adjacent families in cases where boundary adjustments may reduce
the accommodation pressure without requiring excessive transportation times.
The setting and achievement of our priorities will be affected by the amounts of Grant For New Pupil
Places that the Board can reasonably expect to receive.
Renewal and upgrading of existing facilities
As part of the development of a Long Term Accommodation Plan, the Board has contracted with Physical
Planning Technologies Inc. to assemble data on the extent of deferred maintenance and capital renewal
required for the Board's property portfolio, starting with year one (2001) and extending 25 years.
(As amended at Business Services Committee, October 11, 2000 - changes in italics)
16-
The work by Physical Planning Technologies Inc. involves the use of models, verification audits by an
independent professional team, and on -site confirmation by Board staff. The REC_ =.PP program contains
models of the buildings and their physical components in a database that provides the portfolio manager
with the ability to pro - actively plan current and future capital replacement. The program expresses the
cyclical renewal requirements of the components as they occur, with respect to either the original
construction date or the date of their last installation.
The program will assist with identifying the capital investment needed for renewal for all facilities, regardless of age,
over the next 25 years. The most pressing issue is the existing magnitude of deferred maintenance.
Preliminary data indicate that the Board faces an immediate backlog of over $100 million in maintenance
and capital renewal projects. Additionally, it indicates an annual requirement far in excess of the
approximately $9 million in annual funding which the Board currently receives. These assessments
address only building condition needs, not program- related facility needs. This remains to be assessed.
Facilities staff will develop a Maintenance/ Capital Recovery Plan that will outline strategies that will
allow the Board to identify and prioritize the work to be carried out using the Facilities Renewal
allocation. Additionally, Facilities staff will work jointly with senior staff, schools and other stakeholders
to identify critical projects and enhancements to our facilities that are essential to allow our schools to
address the evolving needs of students. Energy Perforniance Contracting will also be explored to assist with
addressing renewal of building system components.
In some cases, the recovery plan may involve the ultimate reconstruction of an existing school if the costs
of renovation and upgrades are excessive. Cost/benefit and life cycle cost analysis will be used to identifij
prioritization options.
Additionally, the Board will need to evaluate the suitability of its current facilities for administrative purposes. This
may result in certain properties being declared surplus and /or identify the need for renovation or relocation.
SOURCES OF FUNDING
The Board will need to prioritize its future capital expenditures in light of the financial`resdtrces
available to it.
The current allocation of approximately $9 million annually for facilities renewal is allocated to cyclical
maintenance and renewal projects and has proven to be inadequate to prevent the continued
deterioration of our facilities.
To address its capital needs, the Board has only the following funding sources:
• Grants for New Pupil Places - Once the Board's elementary enrolment exceeds the ministry capacity,
it becomes eligible for a Grant for New Pupil Places of $1100 per additional elementary pupil. Based
on preliminary projections, staff has prepared three possible scenarios.
1. Appendix A -1 indicates that if no schools are closed, and the Board does not dispose of the three
previously closed schools, McNabb, Borden and Brook Lane, it will continue to have a surplus of
pupil spaces and will not be eligible for these grants.
2. Appendix A -2 indicates that if no schools are closed, but the Board proceeds with the disposal of
McNabb, Borden and Brook Lane, a small deficit in pupil places will occur and would generate a
total of $6 million in grants in total over a period of approximately 10 years. These grants are
(As amended at Business Services Committee, October 11, 2000 - changes in italics)
included in the $3.6 M in Grants for New Pupil Places noted in Report No. 00 -187. This is well
short of our projected needs which are in excess of $68 M.
Appendix A -3 indicates that if the recommendations in Report No. 00 -187 are approved, the
Board will become eligible for grants throughout the 15 -year period. The grant for 2001 -02 would
be approximately $3.6 million. (The $3.6 M Grants for New Pupil Places anticipated as a result of
recommendations in Report No. 00 -187 includes any grant money generated from the closure of
McNabb, Borden and Brook Lane.) Based on current population projections prepared by RMOC
staff, elementary enrolment and the Grant would rise until 2004 at which time a slight decline
begins. In total, the Board would receive approximately $46 million in Grants for New Pupil
Places over the 15 -year period.
• Capital Reserves - as of August 31, 2000 the Board had Capital reserves of $ 3.750 million.
Proceeds of Sales- After the Board has been notified by the coterminous Boards and the Ontario
Realty Corporation that they do not want a school building, (at no cost), the Board may sell the
property and retain the proceeds. The Board realized proceeds of $1.65 million from the sale of
Crichton St. Public School on August 29, 2000; this amount has been credited to the Pupil
Accommodation Reserve Fund. Staff is currently examining alternative methods of marketing the
remaining two schools, Queensway and Parkway, to maximize the return from the sales.
Should trustees accept staff's current recommendations for elementary school closures, it is possible
that some or all of the sites would not be accepted by the other boards. In this case, the sale of these
properties would generate further funds to be applied towards pupil accommodation.
For properties where pupil places are not attached, the legislation allows the Board to sell the property and
retain the funds. This would apply to vacant land as well as surplus administrative sites. The disposal of these
properties is subject to requirements in Regulation 444198 (as amended).
• Education Development Charges - With the changes to capacity calculations announced by the
Ministry in June 2000, the Board is now eligible to develop and adopt a new Education Development
Charge (EDC) by -law.
An EDC by -law levies a charge on new development which is designed to cover the costs of site
acquisitions to provide school facilities for students generated by that new development. The
legislation requires that a background study be carried out containing detailed development and
enrolment projections for the areas to which the bylaw is to apply. It is staff's intention to proceed
with the background study in 2001 should the Board be eligible for an EDC by -law..
As a transition measure, the Ministry announced in March that boards which do not have an EDC by-
law in place may use funds held in the EDC Reserve fund from a previous by -law for school
construction in that part of the board to which the by -law applied. In the case of the OCDSB, this
would be the area of the former Carleton Board of Education. As of August 31, 2000, the balance in
the EDC Reserve fund was approximately $14 million.
• Innovative Approaches Where Feasible
(As amended at Business Services Committee, October 11, 2000 - changes in italics)
/7
PROCESSES REQUIRED TO COMPLETE THE PLAN
Staff has identified the following steps in finalizing a recommended Facilities Master Plan:
• Enrolment projections for both elementary and secondary panels will be updated in
conjunction with a background study, to be carried out in preparation for a new education
development charge by -law;
• Based on those projections, staff will identify and evaluate options for enrolment growth;
• Facilities staff will continue with the implementation of the RECAPP information system
with a view to prioritizing work to be funded through the Facilities Renewal envelope;
• Based on the results of school closure decisions, Planning staff in conjunction with Finance
will develop recommended strategies to finance and fund accommodation initiatives; and
• The plan, containing recommendations for prioritized expenditures and public consultation,
will be presented to trustees and the public.
Among the criteria to be used in prioritizing projects will be:
• program requirements;
• current and projected utilization factors;
• number of portables currently in use, as well as site or servicing constraints on the ability to
add portables;
• health and safety issues;
• availability or lack of alternative accommodation options within a reasonable time and
distance;
• impact on transportation costs;
• likelihood of additional funding becoming available; and
• partnership opportunities.
The above criteria are not listed in any particular order, but are often inter- related.
CONCLUSION
This report has only looked at elementary accommodation needs. It should be noted that the Grants for
New Pupil Places generated by the school closures recommended in Report No. 00 -187 will generate
approximately $46 million in grants over the 15 -year period.
(As amended at Business Services Committee, October 11, 2000 - changes in italics)